In Worthington Hills, starting the week of February 20th, Aqua will begin a waterline replacement project on Circle on the Green. Aqua will replace 6" cast iron main with 4,575 LF 8" DI pipe, 10-8" valves, and 10 fire hydrants. The project also includes 58 - 1" residential service connections.
In Brookside, DLC Equipment is extending the water main on Ione Ct nearest the Brookside golf course. The extension of the water main is to improve the health and safety of the water supply to the Brookside Country Club. The project is scheduled to begin next Monday, March 6th, and end April 3rd, weather permitting. The anticipated work hours are 8 AM to 4 PM.
The plans for both projects are available on the Road Department's Construction Updates page: https://www.perrytwp.org/2263/Construction-Updates